StreetFilterWork DescriptionFilter
Expand/Collapse Suburb : Austinmer ‎(5)
Headlands Ave
25/05/200931/07/20097am to 3pm weekdays (occasionally to 5pm); weekend work may take place to meet completion deadlines.
Reconstruction of car park adjacent to boat ramp and tennis courts.  Access will be maintained to boat ramp for duration of project (except for short periods when working close to ramp).
Current
Buttenshaw Drive
4/08/20094/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Headlands carpark
5/08/20095/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Mountain Rd
18/08/200918/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Wigram Road
19/08/200919/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Scheduled
Expand/Collapse Suburb : Balgownie ‎(1)
Bassett Street
23/09/200923/10/20097am to 5pm daily
Road reconstruction works.  Minor delays anticipated.
Scheduled
Expand/Collapse Suburb : Berkeley ‎(9)
Fred Finch Park carpark
30/07/200930/10/20096.30am to 3.00pm Mon - Fri
Car park improvements to kerbs and carpark surface
Current
Weerona St
10/08/200911/09/20096.30 to 17.00 Mon to Fri
Remove and replace damaged sections of kerb and gutter
Completed
Derby St
31/08/200919/09/20096.30 to 17.00 Mon to Fri
Remove and replace damaged sections of kerb and gutter prior to road repairs.
Scheduled
Barnes St
7/09/200925/09/20096.30 to 17.00 Mon to Fri.
Remove and replace damaged sections of kerb and gutter, tree removals required.
Current
Essex Street  between Kent Street and Sussex Street.
23/09/200913/10/20096.30 am - 4.45pm   Mon - Fri    6.30am-2.30pm Sat
Road Reconstruction with full road closure, access only to service vehicles and residents under traffic control conditions when possible.
Completed
Gallop Street between Nolan Street and Barber Street
6/10/200924/10/2009Mon - Fri 6.30 am - 5.00pm  Sat 6.30 am - 3.00pm
Reconstruction and resurfacing of road pavement, will involve use of heavy plant and equipment.Part and full road closures will apply. The work site will be monitored by traffic controllers allowing access to residents and service vehicles when possible during full road closure conditions.
Current
Cambridge St
5/11/20095/11/20097am to 5pm
Asphalt patching works (weather permitting).  Minor delays anticipated.
Completed
Weerona Ave
26/11/200926/11/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Scheduled
Illawon St
27/11/200927/11/20097am to 5pm
Asphalt patching works (weather permitting).  Minor delays anticipated.
Scheduled
Expand/Collapse Suburb : Bulli ‎(5)
Allenby Parade and Beattie Ave (between Allenby and Princes Hwy)
18/05/200910/07/20097am to 3pm weekdays (occasionally to 5pm); weekend work may take place to meet completion deadlines.
Stage 1 - Allenby Rd - reconstruction of pavement - full width.  Road will be closed to all traffic except local residents.
Stage 2 - Beattie Ave  - reconstruction of pavement and some kerb and guttering. Half road closure at Princes Hwy intersection with detours in place.  Minor delays anticipated.
Current
Trinity Row
25/06/20093/07/20097am to 2:30pm
Installation and replacement of timber log barriers from Ruby's Cafe to Sandon Point
Current
Beattie Avenue (between Princes Hwy & Tyrwhitt Ave)
6/07/200910/07/20097am to 5pm
Road reconstruction works.  This section of Beattie Avenue will be closed to traffic.  Minor delays anticipated.
Current
Hutton Avenue
27/07/200917/08/20097am to 5pm
Footpath works between Hutton Avenue and footbridge linking Hutton Avenue and Beach Street.  Alternative route via Trinity Row.
Current
Trinity and Farrell Roads
22/09/200913/11/20096am to 6pm
Road concstruction from east end of Farrell Road, both sides, to culvert 20m east of Carrington Street.  New kerb & gutter from Jardine Street through to culvert in Farrell Road eastern side.
Half road closure will be in place 24/7 during construction. North bound traffic will be detoured through to Franklin from Carrington and from Franklin down Ursula to access Trinity Row. South bound will not be affected nor will pedestrians or cyclists.
Current
Expand/Collapse Suburb : Coledale ‎(1)
Cokeworks Rd
19/08/200919/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Scheduled
Expand/Collapse Suburb : Corrimal ‎(1)
Foothills Road
30/09/200911/12/20097am to 3pm weekdays (occasionally to 5pm); weekend work may take place to meet completion deadlines.
Stage 1 - Concrete lining of sewer mains - underway
Stage 2 - Stabilisation and rehabilitation of embankments and streambed in James Creek east of Foothills Road. Heavy trucks carrying rock will be accessing the site. Minimal disruption to traffic is anticipatged.
Current
Expand/Collapse Suburb : Cringila ‎(1)
Lake Ave
19/11/200919/11/20095pm to 5am
Night asphalt reurfacing works (weather permitting). Diversions in place minor delays anticipated.
Completed
Expand/Collapse Suburb : Dapto ‎(6)
Unara Road between Princes Hwy and Station Street
21/04/200917/07/20097am - 430pm
Footpath construction works and cycleway installation. Road shoulder closed. No traffic disruptions anticipated.
Current
Kanahooka Rd (Brownsville Ave to Prince Edward Dr)
6/07/200910/07/20097am to 5pm
Road stabilisation works (weather permitting).  Minor delays anticipated. Diversions in place.
  
    
  
Scheduled
Lane 117 and Billabong Street
31/07/200931/07/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Princes Highway
17/09/20099/10/20096.30 to 17.00 Mon to Fri, 6.30 to 15.00 Sat
South bound traffic reduced to one lane Princes Highway Dapto between Baan Baan Street and Bong Bong Road. traffic control conditions apply between 6.30 am - 4.45pm Mon- Fri and 6.30am - 3.00pm sat
Completed
Kanahooka Rd (Prince Edward Dr to Brownsville Ave)
15/11/200919/11/20096pm to 6am
Night asphalt reurfacing works (weather permitting). Diversions in place minor delays anticipated.
Completed
Princes Highway to Prince Edward Dr
15/11/200919/11/20096pm to 6am
Night asphalt reurfacing works (weather permitting). Diversions in place minor delays anticipated.
Completed
Expand/Collapse Suburb : East Corrimal ‎(1)
Aldridge Ave
1/09/20091/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : East Woonona ‎(1)
Park Rd
23/11/200929/01/20107am-3pm
Upgrade of car Park to be constructed first, should be completed by mid december.
Shared cycleway to be constructed at various stages, after car park completion the section between Kulgoa and Beach rd inside Nicholson Park will be constructed including minor K&G at entrance to eastern car park.
Progressing then to the west from Kulgoa to Railway Pde along existing footpath.
Upon completion Pram ramp and Pedestrian Refuge will be constructed at the corner of Kulgoa and Park Rd.
Current
Expand/Collapse Suburb : Fairy Meadow ‎(2)
Bassett Street between Hamilton and McMahon Streets
15/06/200917/07/20097am to 5pm daily
Reconstruction and upgrade to kerb and gutter.  Delays anticipated with access for businesses and local residents under guidance of traffic controllers.
Current
Cabbage Tree Lane
26/08/200926/08/20094pm to 5am (Night Works)
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Farmborough Heights ‎(1)
Carlon Cres
15/06/200917/07/20097.00am to 5.oopm Mon to Fri. 7.00am to 1.00pm Sat
Pipeline replacement in reserve adjacent to 19 Carlon Crescent
Current
Expand/Collapse Suburb : Gwynneville ‎(1)
Sidney St
4/09/20094/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Helensburgh ‎(2)
Walker Street
8/06/200924/07/20097am to 3pm weekdays (occasionally to 5pm); weekend work may take place to meet completion deadlines.
Reconstruction of Helensburgh Swimming Pool Car Park off Walker Street.  Works include some new kerb and gutter and footpaths on Walker Street adjacent to the car park.
Current
Walker St Carpark
9/11/20099/11/20097am to 5pm
Asphalt patching works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Horsley ‎(1)
Homestead Dr and Bong Bong Rd
24/07/20097/08/20096.30am to 3.00pm Mon - Fri
Install missing sections of footpaths at this location
Scheduled
Expand/Collapse Suburb : Koonawarra ‎(3)
Gareema, Kyeema & Wallabah Streets
28/07/200928/07/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Alcoomie & Bingara Streets
29/07/200929/07/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Werowi & Craig Streets
30/07/200930/07/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Lake Heights ‎(2)
Weringa Ave between Karrabah Cr to Anna Ave
11/06/200924/07/20097.00am to 5.00pm Mon to Fri, 7.00am to 1.00pm Sat
Installation of new roundabouts at two intersections, installation of approach islands and pedestrian refuges, all associated linemarking and signage for this traffic facility.
Current
Cnr Flagstaff Rd & Lake Ave
27/08/200927/08/20095pm to 5am
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Port Kembla ‎(2)
Gloucester, Darcy, Parkes, Third, Parker & Charles Streets
5/08/20095/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Marne Street
19/10/20096/11/2009Mon - Fri 6.30 am - 5.00pm
Replacement of approx 75m of kerb and gutter and the installation of 100m of subsoil drainage between Military Road and Electrolytic Street.  The work will involve the use of plant and equipment such as backhoes, excavators and trucks.
The site will be under traffic control conditions.
Current
Expand/Collapse Suburb : Stanwell Tops ‎(1)
Bendena Gardens
27/07/200918/12/20097am to 5pm
Drainage works.  Minor delays anticipated. Stage 1 near completion, works to re-commence mid October.
Current
Expand/Collapse Suburb : Tarrawanna ‎(2)
Caldwell Avenue and Meadow Street
1/06/200921/08/20097am to 3pm weekdays (occasionally to 5pm); weekend work may take place to meet completion deadlines.
Construction of new traffic management facilities on Caldwell Ave and Meadow St on the approaches to the existing roundabout.  Also involves construction of a new footpath on the western side of Meadow St from Caldwell Ave to Wallace Rd.
Completed
Brooker Street
8/07/20098/07/20097am to 5pm
Asphalt patching works (weather permitting).  Minor delays anticipated.
Scheduled
Expand/Collapse Suburb : Thirroul ‎(10)
Lawrence Hargrave Drive & Railway Parade
from Philip Street to Railway Parade - south side
2/02/200931/07/20097am - 3pm Occasionally to 6pm
Footpath, kerb and gutter and traffic light construction works.
Kerbside lane will be closed in construction zone.
Minor traffic disruptions anticipated.

July work will include reconstruction of carpark on corner of LHD and Railway Pde.
Current
McCauley Street
18/08/200918/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Ann St
30/09/200930/09/20097am to 5pm
Spray sealing works (weather permitting). Minor delays anticipated.
Completed
Surfers Pde
30/09/200930/09/20097am to 5pm
Spray sealing works (weather permitting).  Minor delays anticipated
Completed
Craig St
30/09/200930/09/20097am to 5pm
Spray sealing roadworks (weather permitting).  Minor delays anticipated.
Completed
The Breakers
7/10/20097/10/20097am to 5pm
Spray sealing roadworks (weather permitting).  Minor delays anticipated.
Completed
Spray St
7/10/20097/10/20097am to 5pm
Spray sealing roadworks (weather permitting).  Minor delays anticipated.
Completed
Railway Parade carpark
30/10/200930/10/20094am to 10am
Asphalt patching works (weather permitting).  Minor delays anticipated.
Completed
Ocean St
10/11/200910/11/20097am to 5pm
Spray sealing roadworks (weather permitting).  Minor delays anticipated.
Completed
Jaraga Circuit
23/11/20095/12/20098am - 3pm
removal of old drainage system and upgrade with a Turf Swale and concrete with rock armouring at base of swale.
Current
Expand/Collapse Suburb : Unanderra ‎(2)
Carr Parade
14/07/200923/07/20096.30am to 3.00pm Mon - Fri
Remove and replace damaged kerb and gutter
Scheduled
Central Rd & Cnr Highway
28/09/200928/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Warrawong ‎(1)
Cowper St Cnr of Eyre Pl
12/09/200912/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Windang ‎(1)
Banksia & Ocean Streets
17/08/200917/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Expand/Collapse Suburb : Wollongong ‎(8)
Rawson Street Car Park
15/06/200928/08/20097.00am - 3.00pm
Construction/upgrade of car park. Work has already begun with partial occupation of the car park by council work team.
Full closure of the car park is anticipated to occur 20-7-2009 and will be unavailable to the public until approx. 28-8-2009.
Current
Cliff Road
30/06/200931/07/20097am to 5pm
Installation of new shareway to accommodate pedestrians and recreational cyclists on Cliff Road.  During this project, one way traffic will be operating around the work area by temporary traffic signals.  Minor delays anticipated.

In addition, geotechnical investigations involving a specialist drill rig will be operating between 8am and 4pm from 1-3 July on the eastern footpath.  Pedestrians may be diverted during this period.
Current
Cliff Road (between Georges Place and Marine Drive)
16/07/200916/07/20094pm to 5am (Night Works)
Night asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Current
Kenny St - Swan St to Fox Ave
2/09/20092/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Mangerton Rd - Crown St to Rowland Ave
5/09/20095/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Bligh St
7/09/20097/09/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Railway Pde + Governors Lane
13/11/200913/11/20097am to 5pm
Asphalt resurfacing works on footpath (weather permitting).  Minor delays anticipated.
Current
Church Street - Intersections with West and Beach Streets
16/11/200918/12/20097am to 5pm weekdays; 7am to 12 noon Saturdays
Construction of traffic safety improvements at the intersections of Church Street with West and Beach Streets.  Works include new median islands, linemarking of travel paths and kerb realignments.
Current
Expand/Collapse Suburb : Woonona ‎(4)
Hollymount  Car Park Alice St
25/05/200926/10/20097am to 3pm weekdays (occasionally to 5pm); weekend work may take place to meet completion deadlines.
Reconstruction and sealing of car park off Alice Street. Works include construction of some kerb and guttering and improved drainage.
Completed
Cnr of Campbell Street and the new NDE on ramp
23/06/20094/07/20096:30am - 5:00pm Mon to Fri, 6:30 - 2:30pm Sat
New flat top speed and pedestrian hump, and new 2.5 m wide footpath linking to existing
Current
Campbell St
6/08/200911/08/20097am to 5pm
Asphalt resurfacing works (weather permitting).  Minor delays anticipated.
Completed
Kareela Rd/ Beach Dr
7/09/200916/11/20096:30am to 3:00pm
Renewal of damaged cycleway panels.
Current
Expand/Collapse Suburb : Woonona East ‎(2)
Railway Pde (at corner of Park Rd)
30/06/20093/07/20097am to 3pm
Construciton of new concrete footpath at base of new railway station access ramps. Railway Pde left turn lane closed during constructoon hours, minor traffic delays expected.
Current
Park Road at The Circle
3/08/20097/08/20097am to 3pm weekdays (occasionally to 5pm)
Footpath renewal (outside Newsagent - north side).
Scheduled